Capital Projects 2021– August 31 Update
Revised Timelines for UPAR Projects
August 31st 2021

 

The UPAR projects on Henderson Drive, Battleford Road and Service Road are ahead of schedule. All street closures associated with these projects will be posted on our website, Facebook and Twitter pages (@citynb). The revised timelines are listed below:

Henderson Drive (Buhler Avenue to Maher Drive)

Projected completion on September 1st (previously September 4th)

Henderson Drive is undergoing asphalt replacement and is closed to motor vehicles. This includes the Buhler Avenue intersection. The sidewalks are open to pedestrian traffic.

The project is 3 days ahead of schedule and is expected to be opened on September 1st.

Battleford Road Rehabilitation (South Railway Avenue to Highway 16 bypass)

September 10th-16th (previously September 1st to 29th)

Battleford Road will be undergoing rehabilitation. This work includes the South Railway Avenue intersection. There will be impacts to traffic and people should seek alternate routes when possible.

Service Road along Railway Avenue East (Werb Street to A&W access)

September 1st to 21st (previously September 10th-29th)

The City will be undertaking repairs starting September 1st. The Werb Street intersection will not be affected. There will be impacts to traffic and people should seek alternate routes when possible.

Find the latest updates on our UPAR project updates by checking here.

For more information:

David D’Eon, Public Relations
306-445-9155 | publicrelations@cityofnb.ca