City of North Battleford - Saskatchewan
Capital Works Projects 2020
August Update
August 10th 2020

UPAR Logo

100th Street 12th to 14th Avenue

Underground Utility work is complete, with drinking water advisories in place until the new mains are tested and commissioned.  Roadway reconstruction work is underway, with the project planned to be complete on September 26th.  The 1200 and 1300 blocks of 100th Street will be closed to traffic, but pedestrian access to businesses will remain open from the back alley. Downtown businesses will remain open with alternative access in place.   Visitors to downtown businesses are encouraged to plan their trips and to leave a little extra time to find parking.  Motorists using 100th Street and Railway Avenue as a route through the centre of the city are encouraged to use Territorial Drive as an alternate route to get around the city, and to avoid traffic congestion on local roads around downtown while the work is underway. Underground work will be performed by Sanburn Construction, and Roadways by G&C Asphalt.

95th Street 15th to 16th Avenue

Underground Utility work is planned for August 24th to September 4th along 95th Street from 15th to 16th Avenue.  Road closures, water service disruptions, and drinking water advisories will be in place.  Roadway restoration will follow the underground work and is expected to be completed by September 30th.  Underground work will be performed by Sanburn Construction, and Roadways by G&C Asphalt.

 

110th Street 8th to 9th Avenue

Underground and Roadway work is complete and the street is open to traffic.

101st Street 19th to 20th Avenue

Underground Utility work is planned for August 10th to August 21st along 101st Street from 19th to 20th Avenue.  Road closures, water service disruptions, and drinking water advisories will be in place.  Roadway restoration will follow the underground work and is expected to be complete by September 12th.  Underground work will be performed by Sanburn Construction, and Roadways by G&C Asphalt.

Carlton Trail / Yellow Sky Drive Improvements

Underground Utility work is complete and roadway work is underway.  Road closures and lane restrictions will be in place as the work proceeds. Roadway construction is planned to be completed by August 15th.  The work includes constructing a centre median along Carlton Trail to prohibit left turns and through North-South movements at the intersection with Frontier Way, as well as the construction of a new signalized full movement intersection at Yellow Sky Drive, and the extension of Yellow Sky Drive to the North.

100th Street Service north of 20th Avenue Road Rehabilitation

Underground Utility work is planned for September 8th to September 25th along the 100th Street Service Road North of 20th Avenue.  Road closures, water service disruptions, and drinking water advisories will be in place.  Roadway restoration will follow the underground work and is expected to be completed by October 31st.  Underground work will be performed by Sanburn Construction, and Roadways by G&C Asphalt.

Community Airport Partnership runway resurfacing

The project is complete and the runway is open to traffic.  Runway resurfacing work was performed by G&C asphalt.

 

For more information:

Dustin Tungilik MacDonald, Communications Administrator
306-445-1713 | dmacdonald@cityofnb.ca