City of North Battleford - Saskatchewan
Capital Works Construction
Scheduled Projects Updates
May 15th 2017

Hydrant Replacement Program

Work is scheduled to begin May 15th to replace fire hydrants at various locations.  Drinking water advisories and road closures are expected.  Sidewalk and roadway patching will be completed the following weeks.

 

17th Avenue – 105th to 107th Street

Underground pipe replacement work is scheduled to begin May 23, and proceed for approximately 2 weeks.  Drinking water advisories and road closures will be in effect in the area.  Roadway reconstruction is scheduled for the following weeks.

 

105th Street – 11th to 12th Avenue, and 12th Avenue - 104th to 105th Street

Underground pipe replacement work is scheduled to begin May 23 along 12th Avenue between 104th and 105th Street.  Work is then expected to move to the 1100 block of 105th Street beginning the week of May 29, proceeding for approximately 4 weeks.  Drinking water advisories and road closures will be in effect in the area.  Roadway reconstruction is scheduled for the following weeks.

 

101st Street – 11th to 12th Avenue, and 12th Avenue – 100th Street to 102nd Street

Underground pipe replacement work is scheduled to begin June 5 along 101st street and commence for approximately 3 weeks.  Underground pipe replacement work is scheduled to begin June 26th along 12th Avenue, proceeding for approximately 2 weeks.  Street reconstruction will begin once the underground work has been completed and will proceed for a further approximately 4 weeks.  Drinking water advisories and road closures will be in effect in the area.  Access to businesses from 101st Street will be closed for the duration of the project.

 

97th Street – 13th to 15th Avenue

Underground pipe replacement work is scheduled to begin June 26, lasting for approximately 6 weeks.  Road closures and Drinking Water Advisories will be in effect. Roadway re-construction will follow completion of the underground work.

 

99th Street – 12th to 13th Avenue

Underground pipe replacement work is scheduled to begin August 7, lasting for approximately 3 weeks.  Road closures and Drinking Water Advisories will be in effect. Roadway re-construction will follow completion of the underground work.

 

Killdeer Park Development

Underground pipe work is currently underway with roadways work scheduled to begin in June.

 

More detailed schedule information will be provided to property owners as it becomes available.  Updates on the progress of the projects are available at www.cityofnb.ca, or by following the City of North Battleford on Facebook or Twitter.